Hello All,
I am trying to automate my companies timesheet program with P6 through an excel import.
When i populate an activity in the taskrsrc tab with both the resourceid and the actual labor units, p6 imports as expected.
For some activities, however, i have assigned a new resource in p6, and because the timesheet program does not know who is assigned, i do not want to import a potentially different resourceid as it will add a second resource to the activity. When i try to import just the actual units, without a resourceid, p6 does not make the update. ( note there is a resourceid already assigned in p6, just not in the import file).
Is there anyway around this, a way to import actual units without a resourceid -- perhaps a setting or a permission that i do not have?
Thanks!