How do you treat material costs? Given the distinction between expenses and material costs is depreciation, and there is either a Resource tab or an Expense tab (bottom Layout)

. how do you list your material costs-say bulks? There is a Budgeted Material Costs column in the Activity listing, but not on either the Resource or Expense tabs in the Bottom Layout. This is a Level 1 schedule that has two S/Cs (expenses - transportation) and three procurement activities - topsides, jacket, and bulks. I would not normaly list any non-time related item on a schedule, but this is an interesting case - pre-FEED planning/bugeting. Thanks.