Hello, I'm working on a simple plan for an office building. it's some how decided that project life time is double concrete work life time. so, what I'm looking for is productivity rates regarding to concrete work as well as Method Statement for Concrete Work (Foundation, Slabs, Columns, etc....) something to tell me what is my limits instead of putting 140 workers to finish 5000 sqm slab in 10 days.
Regards,
Ahmad Abdrabou.