Hello, I hope I'm posting in the right section.
My question is, How do I control Contractor schedule as a consultant, while I should do cost control on myself (as consultant) for the same project?
If I speak my mind, I'd say, I can do one of the following:
1- Using Primavera P6, I'd make all in one project, then WBS would look like:
1-Project xxx
1.1-Engineering (By Head Office)
1.2-Project Management (By supplied personnel to working site)
1.3-Construction (Where all project products are listed)
2- Using Primavera P6, I'd make 2 sparate projects, one for Consultant work, and the other for Contractor work.
3- Start using Primavera Contract Management for contractor work, and Primavera P6 for Consultant work.
Please advise, thanks in advance.
Ahmad Abdrabou.