Hello Friends,
I have made a schedule, given relationships, costs resources, and assigned baseline and started updating the progress and scheduled it on a specific date date.
It is giving 83.43 Schedule % Complete & 94.43 Performance % Complete as per applied actuals and assigned baseline & data date.
Knowing the fact that, Schedule % Complete & Performance % Complete depends upon Data Date, Baseline, Costs and actuals applied respectively. Is there still a way of altering Schedule % Complete & Performance % complete in Primavera P6
on the same data date on which its showing 83.43 Schedule % Complete & 94.43 Performance % Complete to show 88.88 % and 89.47% respectively ?
Thanks in advance.