A simple but confusing question for me:
The last activity in a chain has no successor (there is only the project end date) and this activity has some positive number as a Total Float value.
What should be the Free Float value for this activity ?
What you always read about the definition of free float is that is looks at the successor of an activity, but what if in this case, there is no successor ?
Should the Free Float value be 0 or should it be equal to the Total Float value ?