Hi colleagues,
I have a project created in Primavera P6 with some activites with activity steps. I opened this project in Asta Powerproject but I can't find a way how can I display the activity steps I created in P6.
Please help me how could I show it in Asta. Thank you.
Best regards,
Leonard