Hi Planners,
A labor resources called Project Manager was assigned to more than one activitiy in the schedule, by mistake instead of enetring 8 hrs as a default units/time I enetred another figure, I detected this mistake when I explored the Resource Usage Profile. Though I changed the default units/time in the resource screen, P6 does not change the budget units for this resource for each assigned activity, so I had to change the budget units manually, is there a way that the budget units changes automatically once the default units/time changes?
Best,
Moutaz