Here I got one problem regarding calendar change. We submitted the baseline and approved from client, in which the calendar used is user-defined 6 working days.
Now, delay happens to project. And when we are doing EOT, the project complete date is 6 month later than baseline finish date. And we found that the 6 working days' calendar used in baseline is only defined until baseline finished date, i.e. after baseline finish date, 7 days working calendar will be applied to activities.
So, is that ok to revise the calendar in baseline when doing the time impact?
What would you do if you are the contractor? and if you are the client, Would you accept above change when you are reviewing EOT programme?