Hi,
I have been struggling with this problem for some time now and have not managed to resolve it.
It is a fairly large program so it would be useful to find the solution to my problem.
I usually review the activities and update each one with the reported progress and status.
Once I have done this I want to progress the the data date.
I go to tool update progress and select the new data date and apply.
The project is updated.
BUT!
some activities have which should not be have been changed to completed.
I have to do a manual exercise each time to put it back in progress and apply the correct percentage and finish dates.
This is an unecessary time consuming exercise.
Any suggestions?