Hi everyone,
I have a schedule where all dates are entered in days. This is shared on a live server.
I somehow now have a schedule with some activities having a total float of above zero but less than 1.
As a result, on a reset to default F9, some activities show zero float but not critical.
I know of a hundred ways to show these as critical, however, I would like the default settings to show this without any tinkering.
How you would approach debuging these less that 1 day floats?
notable hints are: Floats with 0.11 or 0.10 values, calendars with 9h/d, 5d/w and 10h/d, 7d/w etc.