While tracking the project schedule i am finding problem. Some activities taking more duration then it was planned, so while updating the schedule i have entered actual start, remaining duration. Then the % completion is taking automaticallty. But the project summery task % completion is showing very much higher then it actually completed. How to solve this. Is there any other process to do the correct tracking. It will be very much help to me if anybody can answer me.