Dear All,
I have a situation.
as this week i update the program total performance complete is more than scheduled but when i prepared cost based S curve the actual value for this month is coming less than planned for the month (if i go through budgeted and actual manpower it is showing logically correct values) please help
scenario
my project is divided in two segments
Villa and Infra
villa is ahead of Scheduled with positive float
Infra is behind the scheduled with negative float
project level actual performance Percent Complete is more than scheduled Percent Complete with negative float