Helllo,
I have the must finish by date on the project set to Oct 12 2015. But why would the late finish date be earlier than the ealry finish date? I understand the negative float is due to the project being behind. See snapshot below.

Helllo,
I have the must finish by date on the project set to Oct 12 2015. But why would the late finish date be earlier than the ealry finish date? I understand the negative float is due to the project being behind. See snapshot below.