Hi, I have been working in a Project with duration of 9months, supposed to complete by Sep'13. Due to various alterations in the Finishing Schedule and Nomination of new works, the project has been dragged till date, with every day addition of new works.
Now, the Management has asked us to submit an impacted program for depicting delay incurred, basically for claim.
Kindly advise, what should be the approach as the baseline program has nearly lost its orginality due to numerous changes.