Has anyone successfully countered the USACE's position on rejecting a schedule with redundant ties? My position is that there is constructive logic and preferential logic in a schedule and that both are legitimate. I don't think the corps specs refer specifically to redundant logic but their representatives are misinterpreting the language for their benefit. As far as I can see the justification for clearing redundant ties is to limit clutter and make it easier for Fuse to run risk analysis...I could care less about either of these and want the owner out of my schedule. Thoughts?