Dear All
I am working on a project which started 2012 & finish date is 2019, Mining project. I prepared the project & got all cost variance as per planned & actual with delay analysis. Now we need to find the [strong]cost overrun [/strong]compare with the project report (DPR) which given by one of our consultant 2 yrs back. How to do ??
should I prepare activity wise consultant report in P6 then running Claim digger ??
* using P6 8.3 EPPM
* All cost is incurred on expenses wise because most of the work done by vendors.
Pl guide me ...., Thanking you in Advance.
Regards
Madan Mohan