Hi folks,
Critical path is the sequences of activities which their Total float is 0. When this sequence is defined, it is already late to take countermeasure,
I need to determine earlier the sequence of activities which would delay the project finish date.
Should I fix a threshold of the total float? How would this sequence be called? , sub critical path , near critical path ?...