Dear all,
In a schedule that I used the same calendar for all the activities I experienced the fact that for some activities on critical path the late dates were earlier than the early dates.
e.g. ES:1-MAR-2014 LS:28-FEB-2014 late start one day before the early start, while what I expected was to happen the same day 1MAR2014.
Any ideas?