Dear Forum I have following question....
In MS Project it is possible to setup a dedailne for an actvity and this deadline bar (actually it is an arrow) can be appeard on bar chart.
How to do the same in P6.... so to have an activity bar with some start/finish dates and an additional "bar-like" object for example an arrow like in MS project that specifies the deadline visually on bar chart...
Thanks