Hi,
We got an EOT approved and submitted the last updated program complying the new project finish date. I submitted the updated schedule as the revised baseline. Now when I maintained the baseline (Save a Copy The Current Project) and assigned accordingly I inserted the columns “BL Project Start” and “BL Project Finish” I am getting a date 93 days later then the data date. Then I updated the schedule at the current dated, and the finish of project projected to 45 days ahead of current date but the BL Project Finish is still the same (93 days ahead of our cutoff date). I removed the baseline and deleted from the data base but those dated are still there.
How can I show the new project finish date in the BL Project Finish column?
Cheers - Tanveer