Dear All,
I need your help
Why
1> when i assigned baseline with the updated Sch. i found the percent on (performance % complete) column changed
from 41.06 % to 40.92
2> How i could compare between base line and the updated
when i showed (planned value, actual value, remainig value, budget value) not right values like example
remaning value + actual value Not equal Budget total cost
and planned or Scheduled vlue - Actual value Not equal variance value
3> and why actual cost column give me value equal zero although performance % complete equal 41.06%
thank you for help