Hello,
I am trying to incorporate a productivity factor to my hours to finish the project to show an accurate spread of hours/resources needed in Histograms. However i don't want to change my remaining to earn hours (for S-Curves). Ideally i would like to use the ETC that is calculated using a PF factor, but I can't get the ETC hours to spread in a time distributed report. Does anyone have any suggestions on how I can achieve this?
Thanks in advance.
K