Hi. I'm doing a feasability analysis for an early fase project. I'm trying to build different scenarios with respects to resources and time. I have around 100 activites. I've set Original Duration and Budgeted Labour units. When i use Shift+F9 i still get over-allocated resources. In the schedlog.txt - 4 activites are listed as "Activites that cannot be leveled". I see no reason why they cannot be leveled. Any clues?
Cheers
Haakon