Morning all,
Can you help at all? I've been sent a project in P6 which I've imported and taken a baseline so that future versions can be measured. however the dates on that baseline are differnt from the project it was taken from. one has altered by a week and another by a few days. I can't understand why it would do this given it's a snapshot of the project I'm looking at.
Also another quick one why has in some cases the duration changed but not changed? My project shows an activity as 15days, and after baseline and schedule it's still 15days but when I show the Baseline duration variance it's showing a difference of 7.5 days and it's claiming that my baseline duration is 7.5days but neither start or finish date have changed!
Any ideas more than welcome.
thanks in advance,
Thom