Dear All
when i am updating my program i noticed that in some WBS nodes, all the activities for example have -13 days float, but the last activity in this WBS has a -11 days float, whats the explanation for that ??
this issue has been repeated in other WBSs, and also i noticed that some activities have total float -32 days but the project completion milestone has only -20, any explanation for that too ??
regards,
Rami