hi to all, here i am wondering a way to update my Recovery Schedule and Baseline @ one time by export & import method. I have same activity, duration, relationship in both schedule but my priority is to update my recovery schedule first & in the same time i want to update my baseline schedule with same actual percentages & dates. would you please advice me which procedure i should use because i don't want it to update again & again. Thanks.....