hi every body,
i want to ask something concerning actuals. Does any body here update actual cost for activiites with real cost , not the earned value ? we do this for WBS level on Excel sheet in order to implement EVA.
i think it will take a big effort to calulate actual cost for each activity, how do you do it? what do think the best approach for this.