This problem is basic so I can't help but think I'm missing something really obvious.
When I open a new Powerproject docuement, after I enter a start date for each task, the duration sets itself at a default of 1 week and then populates the finish date accordingly. If I attempt to manually enter a different Finish date Powerproject adjusts the Start date to ensure the duration remains constant at one week. How can I adjust the settings to allow me to populate the Start and Finish dates myself, with the duration then calulated based on my input?
Any advice is appreciated.
Regards,
Paul