Hi All,
I have an easy beginner question. I have a resource-loaded schedule and put in the reamining durations and actuals in place. The data date is somewhere in the middle of the projet lifetime and I need to get the forcast for futre time intervals based on 10 day shift. I have no problem get the planned hours from inception to completion but for the EVs and future forecast, how can I get the values based on the remaining durations and remaining resource units that I have in my system?