Hi All.
Can anyone please help?
I am trying to creat a level of effort activity and have linked it as a SS with its predecessor and FF with its successor both with zero lag.
When I schedule, the level of effort activity only shows the start date as start and finish date with zero duration. I have tried putting the number of duration and finish date manually but it goes back to showing start date with zero duration and a negative float of 1 as soon as as I schedule.
Please help.
Cheers!
Patosaks