Dear all,
I am just wondering, is it possible in Spider to put a condition, that a successor activity shall start within certain time after finish of predecessor?
One can think of plenty technological limitations, when one activity does not necessarily start immediately after the 1st one, but must start within certain period.
Regards.
Evgeny