I just noticed, that Spider allows, when providing actuals, to have Activity duration to be independent of resource work duration.
In the example below the activity has finished earlier, than resource has stopped working on it.
Is is something which has been missed in the software or this is done on purpose?
I seem not to be able to think of real life situation, which would be modeled by such behavior of the software.
In the example below it also creates a problem, because Activity 2 has 2 days lag after Activity 1, which is not being obeyed in this case (assuming Actuvty 1 duration in reality shall be equal to duration of resource work on this activity)
https://docs.google.com/file/d/0B1FBt_G3gCVqTW5MRzVQNElyeVE/edit [1]