I have an activity in which I know the exact date it will finish, however I am having trouble adjusting the finish date in my schedule.
All predecessing activities have been completed, so it's not being pushed back because of that.
Additionally, I have set a "must finish"constraint on the date it will finish, along with an expected finish date that is the same.
When I try and change the finish date I get an error message stating "Remain Finish Date cannot be earlier than Remain Start Date." My start date was over a month ago. Duration type is "fixed duration & units".
Any idea why it won't allow me to change the finish date?
Thanks very much,
B