I made programme and added the mandatory finish to last activity. Each activity in the programme link to each other
I updated the programme with BL finish showing 31st Aug13 and Finish column showing 10th Jan'14. Still I unable to get the total float on project summary first row, Why? Total float value showing is zero.
According to BL finish date and finish date, it must need to show negative float of say 4 months 10days.
Can anyone answer?