Dear All
Discrepancy of the approved drawing and the scope of work under contract clause, would like to submitted letter (site query) to client to clarify the dispute, because the issue for contruction drawing doesn't indicate some components in the construction drawing and the client required to do the work as per the scope of work but not in the contruction drawing.
Any advise
Regards
Ronron