Dear sir,
I am working in the planning division of the refinery and is required to genertae the planned and actual progress of a refinery turnaround jobs on a daily basis to the top management.
How to do this in MSP.I have an initial schedule.I have not alloted resources to activities as the number of activities are large.The different jobs involved are exchangers,columns,vessels,line hydrotest,catalayst loading of reactors etc.Most of these jobs are carried out by cotractors.
Kindly advise.
can you please send me the sample of refinery turnaround schedule
Regards
Sunil.k