START Date:
January, 2003
END Date:
January, 2006 Sienior Planner - AMEC Construction of London Heathrow Terminal 5 Airport Project - Resonible for delivery of Power / Substation construction and Airfield Civils, Fuel Farm, Pavements, etc. - BAA Framework Contract Value circa £5,000m