Dear all,
May be it is a stupid question, but I could never understand the reason to use lags in links between tasks. In a simple FS link, lag would mean, that one task can only start with some delay after the first one has finished. However in reality there must be some reason for this delay (e.g. paint will dry or whatever). So in this case, why not just add an extra task with the duration of a lag? This will make the schedule more transparent also will allow more flexibility in controlling the lag as one can add also calendar, comment, give it a miningful name etc.
So, why would someone use a lag in a link then as an opposite to adding of an extra task ?
Regards.
Evgeny