Dear all,
I'd like to know the right precedure of updating a schedule, Is the following steps of updating a schedule right or not?
"Input actual progress data(including of actual start ,actual finish, remaining duration and so on )"----"apply actuals"----"schedule(F9)"------"store period performance" .
Is "store period performance" the last step or "schedule(F9)" the last step? I saw both of them in another forum. can anyone help me regarding this ? Thanks in advance.
Regards,
Shiguo