I am using P6 v8.2. I have one resource for all activites and I have not statused the schedule. I have changed any resource curves but even if I do, it does not seem to do anything. Why does my S-curve look like a set of steps? More pointedly, why does my summary schedule not evenly distribute budgeted cost over the course of months as opposed to just front loading it at the begining of the month? Help is appreciated.