I am exploring the way that how to assign weights to my schedule
I am using cost & resource loaded schedule
Duration Type = Fixed Duration & Units
% complete type = Duration
Duration % complete = 12.33%
Schedule % Complete = 20.35%
Performance % Complete = 17.89%
Here I want to know the way of assigning the weights to each activity coz my manager is asking to show me the planned weights & Actual Weights.
Thax in advance…… J