Hi, I'm planning a project with a lot of seasonal work. The season is usually from 1. april until 31. of november.
The activities are usually 5 months in total, and the project would not want the contractor to stay on the project over the winter.
Is there anyway to "force" the activity to stay within one season (or year), and if its pushed out in time, it would jump to the next year?
Sincerely
Hawken