Dear masters,
I need your help to clarify my problem with Overall % calculation of schedule&performance % calculation.
In my schedule : Activity Percent complete type: physical% complete. In all activities I manually enter Physical% complete. Acivity type: Task dependent. No resource dependent and no wbs summary activities. Duration type: Fixed duration and units. And the scheule is resource loaded. With this same configuration in another project schedule% complete and Performance % completes are rolled up, but in this project is not.I attached pic of schedule.Please look at the pic,at the engineering activities both schedule and performance % completes are rolled up, but at the procurement activities it is not roll up.Have you any solution? Thanks,In advance.