Hello Planners,
one customer of mine is using a large number of baselines with his projects, more than ten actually
he says that, because he frequently restores and reassigns baselines to Primary/Second/Third baseline, Primavera P6 is displaying links between the current project and a restored baseline; some activities show both correct relationships with aother activities in the current project AND dummy links with activities in the baseline project, identified with the Project ID column in the Activity Details Form, Pred/Succ tab
does somebody have an explanation of this behavior, and know how to suppress these dummy links?
Thanks, Alexandre