Hello;
II am working on a schedule containing around 5000 Activities.Around 3000 Activities Are completed and others are in progress.My manager has asked that create a new schedule containing only the activities that are in progress or not started.Now what trick I should do.i have tried following 1-I filtered the activities that are in progress or not started and exported the schedule but of course it will not export only the filtered activities but it exports the complete project.so of no use. 2- I opened the two projects togather.Copied activities of one project into other but it is only copying the activities not WBS. 3-In WBS Window you can not filter. Please suggest me the solution. Regards