Contractor has submitted an updated schedule and the cost data (Budget at Completion or Budgeted Cost) for newly added activities is importing incorrectly. The contractor sent me a screenshot of his activities and I can see the correct costs. Yet when I import the file, the costs reset themselves to either $8 or $40.
I have received numerous other schedules from this particular contractor in the past and have not had this issue. I have received updatse from other contractors and have not had this issue. It leads me to believe that there is a setting or bug somewhere. The contractor is using version 7.0 and I'm using 8.1. Any suggestions would be helpful.