Hi All
I am Using Primavera P6 Version 8.2.
I have made a programe that is neither loaded wioth cost nor with resources.I am using Duration % Complete.After assigning the current project as baseline when I have updated the schedule I Found that Schedule % Complete is not rolled up to the summary Level.It is entered in front of each activity but not showing in the TOTAL "Band".Same is the case with PErformance % Complete.
Can any one tell me that what I am missing here
RegaRDS