I am using MS PROject to track my project progress and to find the cost and variances for my project.
under view->tables->tracking I am able to track my project. one of my project requirement said, "a task actually started 2 days late" my question is do I change the "actual start" date for the task to 2 days late? I am very new to ms project so I wasn't sure how to do this.
-my next question is to do with SPI. my project SPI is 0.8, but i was asked if having a SPI at 0.8 then to SPI at 0.55 good or bad?
-my project CPI is 0.95, my question is, how can I keep CPI at a constant to derive a new project cost? is this done in ms project?
-what does TCPI of 1.03 mean?
thank you in advance for your response and if i am asking in a wrong forum please let me know where to post.