Need help please.... Why is it that Original Duration in the Summary Level will change equal to Remaining Durationafter I update some activities??? Due to this reason my Duration % Complete in the Highest or Project Level will always be 0% since Duration % Complete is computed based in the formula D%= (Original Duration (Current Duration) - Remaining Duration / Original Duration (Current Duration) * 100. Thanx for your input.